The front entry project has officially started in full force. Southwest Paving is now removing asphalt and will start the grading in the next day or two. Hartman has started the renovation of the first tee also, so there is a lot going on at the club right now. Projected entry project completion time is Mid October. Oh yeah, on top of all that it is aerifying time again. We completed the front nine greens today, plug-collect-sand-drag-brush-mow-water. We did not get the fertilizer down at this time because the winds were blowing 20+ mph all day, it was great for drying sand but not for spreading fert. We will get it down as soon as the winds calm and allow us to.
Labels:
aerification,
aerify,
air exchange,
clubhouse,
construction,
fall,
fertilizer,
projects,
recovery,
renovation,
weather
Tuesday, September 13, 2011
Aerifying Schedule
Last week we aerified greens, and it went about as smooth as it ever has. The weather was absolutely perfect and at a week out the greens are healing nicely. My previous post gives a pictorial of the process from start to finish, for those of you who might be interested in what it takes to go from really nice putting surfaces to something akin to putting over large holed pegboard. By this coming weekend they should be in pretty good shape.
This week we will be aerifying tees, which we started today by getting half of the driving range tee done. Wednesday and Thursday we plan to do the front 9 and back 9 respectively. And then on Friday we plan to finish the driving range tee. The process is a bit different then greens. We pull cores, pulverize them, and then drag the sand/soil into the turf canopy. The par 3 tees and some of the par 4 tees will get some seed and topdressing as part of the process also. Like the greens, we will be mowing the tees a little less frequently over the next week or so, and also waiting a little longer in the day so they have time to dry a bit and we don't track around any mud.
Fairways will follow next week and it usually takes a couple of weeks to get them all done. We use large solid tines and the disruption to play is minimal. They will also get some seed and topdressing dragged in where we feel it is needed, though they have recovered very nicely from the summer issues we had a couple of months ago.
This week we will be aerifying tees, which we started today by getting half of the driving range tee done. Wednesday and Thursday we plan to do the front 9 and back 9 respectively. And then on Friday we plan to finish the driving range tee. The process is a bit different then greens. We pull cores, pulverize them, and then drag the sand/soil into the turf canopy. The par 3 tees and some of the par 4 tees will get some seed and topdressing as part of the process also. Like the greens, we will be mowing the tees a little less frequently over the next week or so, and also waiting a little longer in the day so they have time to dry a bit and we don't track around any mud.
Fairways will follow next week and it usually takes a couple of weeks to get them all done. We use large solid tines and the disruption to play is minimal. They will also get some seed and topdressing dragged in where we feel it is needed, though they have recovered very nicely from the summer issues we had a couple of months ago.
Labels:
aerification,
aerify,
air exchange,
drainage,
driving range,
fairways,
greens,
mowing,
recovery,
seed,
tees,
topdress,
weather
Wednesday, May 18, 2011
Hole #16, What's Going On.
05-10-2011
05-10-2011
05-11-2011
05-16-2011
05-17-2011
Here are shots to summarize the work so far of the bunker renovation taking place on hole 16. It is expected to be completed by the end of the day today and sod should go down tomorrow sometime. In about 2 weeks we should be able to open up the new bunkers and surrounding rough providing the weather cooperated and the new turf roots down good.
And on another note, #16 green will be open for play starting Monday the 23rd. We have kept the height of cut a little longer compared to the other greens to encourage better growth, especially once it starts getting traffic, and overall it is in great shape. There are still some thin spots but the bulk of the damage down the center of the green has recovered very nicely. Once the younger plants have matured a bit more we will start a topdressing program, same goes for #7 green, which should help with the thinner and uneven spots...
If this weather can start to stay more typical for this time of year we should have the turf back in no time.
Labels:
16,
bunkers,
construction,
damage,
greens,
projects,
putting green,
recovery,
renovation,
seed,
seeding,
seedlings,
topdress,
traffic,
turf,
turf loss,
winter damage
Wednesday, April 27, 2011
Progress on #16 Green
( 2011_04_05 - #16 Green )
( 2011_04_22 - #16 Green )
Here are before and to-date snapshots of #16 green, we seeded and covered on the 13th of April. While we do not see a lot of seed germination taking place, the weather even with a cover has made it difficult, the good turf under the cover has become much more vigorous then anything left open. We'll keep you up to date...