Showing posts with label pond. Show all posts
Showing posts with label pond. Show all posts

Saturday, April 7, 2012

Why The Low H2O?


When we drained the pond on #6 down last fall we noticed the muskrat control netting had slipped down a few feet in spots and there were some burrows in the pond bank.  With everything going on this spring so far we have not had a chance to rebuild the small portion that got dug out and also install some new netting up higher on the bank.  Another issue with the pond is the gate system has rocks in the bottom of the enclosure that is preventing the bottom gate sections to seat properly and seal water off from draining out.  This coming week we will climb down and pull the rocks out, and also start to rebuild the pond bank and install new muskrat control along the pond bank.

In other news, we have been very busy tidying up the multiple projects we had left over from last fall/winter.  The tracks from the work on the irrigation pond have been cleaned up and sodded over in front of the 13th green.  The drainage on #15 & 16 has been cleaned up and prepped for seed/sod.  Some of the smaller stumps have been ground up and the holes cleaned out.  The larger ones are too big to feasibly do in-house so we will hire out their removal.  Most of the landscape beds have been cleaned out and are awaiting a fresh layer of mulch.  And to go with all of that we have already started some normal rough mowing routines and are getting closer to a regular mowing schedule on fine turf areas (kinda crazy considering it is only April 7th).

Friday, March 30, 2012

Pump House Flush

We had some spring cleaning in the pump house yesterday.  Every spring over the last handful of years we have had Midwest Elevator out with their airlift system to remove debris from the bottom of the wet well inside the building.  As part of that process we have to remove the check valves and turn them around so we can back flush the pump screens and churn up the water in the wet well.  It went very smooth and we removed a fair amount of stuff such as leaves, small sticks, and even the remains of a squirrel.  Since we did the pond work last December we are hoping this could be one of that last times or at least we can space out the cleanings to every few years.  It is not that much of a hassle but wrestling around 6" check valves and steel couplers can get a bit tiresome.  Pond work?  Well, we extended the wet well intake about 4' and raised it about 24" off the bottom of the pond.  The old inlet was flush with the bottom and allowed all sorts of debris into the system.  So between the two jobs we should be clean and good to go for years to come...

Monday, July 19, 2010

How Much Peat? Or Organic Matter for that matter...


( 2010_07_19 - Soil Boring #14 Approach )

In an effort to better understand what kind of soil structure, or lack there of, we did some soil borings on #14 approach today. With the pond banks collapsing, the bunkers in need of renovation, and the approach a rolly-polly expanse, the greens committee is starting the planning process for what will take place over the next couple of years. The amount of organic matter, specifically peat, has always been in question in that area. And with renovation plans beginning we needed to get a handle on what exactly we are dealing with in the area.

( 2010_07_19 - Soil Boring on #14 Approach )

From the looks of things as the cores were coming out, we are not in a situation where we will need to excavate any substantial peat. The soil profile appeared to be made up of about 4 feet soil & peat, then about 2-3 feet very sloppy wet gray clay, and then down to the boring depth of 20 feet it was generic looking clay. Braun Intertec will be compiling a report on the profile and getting that back to us. With that general knowledge we should be able to come up with a pretty good game plan for renovation of the general area. It's nice to know we don't need to dig up 15 feet of junk and then fill it all back in with some proper soils for good growing conditions. 

Wednesday, February 13, 2008

The work on #6 began back in December on the 11th & 12th. With a hoe and dozer Nyen Construction completed the rough work by removing the bunkers and bringing the pond edge closer to the green complex. All of the excavated soil was incorporated into mounding on the left and back left corner of the green complex. The excess was graded out into the no-mow area behind the pond. In the spring Hartman Golf will be back out and finish up the final grading and sod install. Just so everyone is aware, the pond level will be kept at minimum until the project is completed. Because of that, the aerator/fountain will not be put in until the water level is brought back to normal. The pond project on #6 is only one project that needs to be completed this coming spring. Those of you who have visited the club this winter have seen the addition of evergreen trees along the County Road 30 side of the driving range tee. All the trees were transplanted from the golf course so there are 20+ tree spade plugs that need to be leveled and sodded. The forward tee on #2 is also still under construction and will be finished as soon as the soil can be worked. As with other the other tee projects, that one will be sodded and should be ready for play very quick. There will be plenty to keep us busy along with getting the course ready to open.

For a current update on the golf course: The snow cover has been good all winter and that is a good thing with the very cold temps & wind we have had on occasion. And now there is a chance for a few more inches which would nicely cover the exposed mounds and turf areas we do have.